GOELERS Solutions was appointed to carry out the supervision and control of the compliance upgrade works for the HTB/HTA substations at Glazoué and Paouignan.
This project involves upgrading the high and very-high-voltage transformer substations to bring them into compliance with current standards. The supervision and control mission covers activities such as planning, coordination, inspection, monitoring, and validation of the work carried out by contractors.
The objective of this project is to ensure the proper functioning and safety of the electrical infrastructure at these two substations, guaranteeing a reliable and secure power supply for the communities they serve.
GOELERS SOLUTIONS' technical base in the town of Dassa
Site visit by the mission lead and experts at the Paouignan substation
Building of the 63kV/20kV Paouignan source substation
Visit by the UGP (PASE/SBEE) delegation to the Paouignan site
Visit by the UGP (PASE/SBEE) delegation to the Paouignan site
Handover of the Paouignan site to the Environmental and Social audit firm
Handover of the Glazoué site to the Environmental and Social audit firm
Construction work on the Glazoué substation building — interior drainage channels
Construction work on the Paouignan substation building — slab waterproofing
Foundation works for the substation building — rebar and formwork
Slab pouring at the substation — rebar placement